BC1 Percentage of domestic full plans applications receiving a first assessment within 21 days from date of receipt;
81%
BC2 Percentage of non-domestic full plans applications receiving a first assessment within 35 days from date of receipt
93%
BC3 Percentage of resubmissions (amended plans/ information) assessed within 14 days;
84%
BC4 Number of completions per annum/ Number of commencements per annum expressed as a percentage;
70%
BC5 Percentage cost recovery of the Building Regulations Service.
With Corporate Support Costs–61%
Without Corporate Support Costs–79%
Council |
BC/1 |
BC/2 |
BC/3 |
BC/4 |
BC/5 |
Antrim |
69% |
64% |
88% |
127% |
80% |
Ards |
55% |
86% |
69% |
123% |
96% |
Armagh |
72% |
83% |
81% |
78% |
79% |
Ballymena |
44% |
64% |
65% |
64% |
68% |
Ballymoney |
|
|
|
|
|
Banbridge |
87% |
79% |
N/A |
N/A |
79% |
Belfast |
88% |
88% |
75% |
122% |
82% |
Carrickfergus |
19% |
24% |
100% |
147% |
73% |
Castlereagh |
87% |
88% |
86% |
166% |
81% |
Coleraine |
68% |
62% |
89% |
92% |
55% |
Cookstown |
100% |
100% |
92% |
125% |
76% |
Craigavon |
88% |
100% |
86% |
92% |
77% |
Derry |
|
|
|
|
|
Down |
61% |
61% |
56% |
100% |
68% |
Dungannon |
87% |
81% |
89% |
117% |
89% |
Fermanagh |
85% |
80% |
90% |
99% |
101% |
Larne |
63% |
86% |
26% |
125% |
31% |
Limavady |
91% |
95% |
95% |
93% |
53% |
Lisburn |
99% |
100% |
96% |
127% |
102% |
Magherafelt |
46% |
40% |
95% |
197% |
103% |
Moyle |
92% |
89% |
94% |
98% |
62% |
Newry & Mourne |
60% |
84% |
50% |
85% |
84% |
Newtownabbey |
95% |
90% |
86% |
98% |
57% |
North Down |
61% |
79% |
70% |
83% |
66% |
Omagh |
67% |
68% |
61% |
78% |
47% |
Strabane |
95% |
100% |
88% |
100% |
55% |
BC/1 Percentage of domestic full plan applications receiving a first assessment within 21 days from date of receipt.
BC/2 Percentage of non-domestic full plan applications receiving a first assessment within 35 days from date of receipt.
BC/3 Percentage of resubmissions (amended plans/information) assessed within 14 days.
BC/4 Number of completions per annum/ Number of commencements per annum expressed as a percentage.
BC/5 Percentage cost recovery of the Building Regulations Service.